Building Timeline
| Nov. 29, 2001 | Approval of Project Initiation Request of Academic Planning Committee |
| Jan. 16, 2002 | Draft Program Statement reviewed by the Aesthetic Review Committee |
| Mar. 1, 2006 | Student referendum approving funding of 50% of project costs |
| Aug. 1, 2006 | Revision of draft Program Statement |
| Sept. 11, 2006 | Project Review Board approves Program Statement |
| Oct. 3, 2006 | Program Statement to UNCA |
| Nov. 3, 2006 | Board of Regents approves Program Statement |
| Nov. 6, 2006 | Begin architect selection |
| March 2007 | Board of Regents approves architect selection |
| March 2007 | Start design |
| March 2008 | Complete design |
| May 2008 | Bid project |
| June 2008 | Start construction |
| December 2009 | Complete construction |
| February 2010 | Open building |
Funding for the Multicultural Center
The new multicultural center will be named the Jackie D. Gaughan Multicultural Center in honor of John Gaughan and his family's capstone gift that was announced on Friday, April 13 at the Ross Media Arts Center. [See DN article] |