Production Schedule 2007-2008
| |
|
Self Defense |
Six Degrees |
American Daughter |
Carousel |
Unvarnished Truth |
| Week 1 |
Brainstorming |
4/1 |
8/26 |
10/28 |
11/4 |
1/6/08 |
| Week 2 |
Concept finalized-all areas |
4/8 |
8/26 |
11/4 |
11/1 |
1/6 |
| Week 3 |
Rough set sketches/Floor plan |
4/8 |
8/26 |
11/11 |
11/18 |
1/13 |
| Week 4 |
Revised set sketches/ Light & Sound analysis |
4/15 |
8/26 |
11/18 |
11/25 |
1/20 |
| Week 5 |
White model & Costume sketches |
4/22 |
9/2 |
11/25 |
12/2 |
1/27 |
| Week 6 |
TD: costs and labor estimates |
8/26 |
9/9 |
12/2 |
12/9 |
2/3 |
| Week 7 |
Designer Elevations, Light sketches/ideas/photos |
8/26 |
9/16 |
12/9 |
1/6/08 |
2/10 |
| Week 8 |
Construction drawings, detailed props list, costume designs |
9/2 |
9/23 |
1/6/08 |
1/13 |
2/17 |
| Week 9 |
Color model, tendering, volor costume sketches |
9/9 |
9/30 |
1/13 |
1/20 |
2/24 |
| Week 10 |
Build starts, rough Light plot |
9/16 |
10/7 |
1/20 |
1/27 |
3/2 |
| Week 11 |
Light section, masking set, lineset index |
9/23 |
10/14 |
1/27 |
2/24 |
3/9 |
| Week 12 |
Light plot, color order (Sat/Sun: light hang) |
9/30 |
10/21 |
2/3 |
3/2 |
3/23 |
| Week 13 |
Set Load-in, Sat/Sun: Light hang & focus. Final props list |
10/7 |
10/28 |
2/10 |
3/9 |
3/30 |
| Week 14 |
Set Load-in, Focus, rough Light cues |
10/14 |
11/4 |
2/17 |
3/23 |
4/6 |
| Week 15 |
Paper Tech, Dry Tech & 1st Tech |
10/21 |
11/11 |
2/24 |
3/30 |
4/13 |